Site Plan — Orthomosaic (14 Nov 2026)

D-1 D-2 D-3 D-4 Gas Holder Compressor D-01 D-02 D-03 D-04 D-05

360° View — Capture Point CP-12 (Digester D-2)

for (let i=60; i<=540; i+=40) { } D-02: Wall 300mm Short Capture: 14 Nov 2026, 10:22 • Heading: 45° • Pitch: -10°

Deviation Register — Filterable Table

ID Element Location / Grid Type Design vs Actual Difference Tolerance Status Owner Evidence
D-01 Digester-2 Raft Foundation Grid B-3 / D-2 Position Design: 0,0 → Actual: +180mm E, +45mm N 180 mm East 50 mm Open Site Eng. - Kumar
D-02 Compressor Plinth C-201 Grid E-7 / Comp. House Dimension Design: 3000mm × 2000mm → Actual: 2700mm × 2000mm 300 mm Short 25 mm Open Struct. Eng. - Patel
D-03 Pipe-Rack Pedestal P-7 Grid C-5 / Pipe Rack Missing Design: Present → Actual: Not Found — N/A NCR Raised Piping Lead - Singh
D-04 Gas Holder Foundation Ring Grid D-4 / Center Position Design: Center (0,0) → Actual: +220mm S, +80mm W 234 mm SW 75 mm Under Review Vendor - GAIL
D-05 Pipe-Rack Anchor Bolt Group Grid B-5 / Pipe Rack Position Design: 200mm spacing → Actual: 185-215mm variance Up to 15 mm 10 mm Closed QC - Sharma
D-06 Control Room Building Corner Grid A-1 / Admin Dimension Design: 12000mm × 8000mm → Actual: 12050mm × 8000mm 50 mm Long 25 mm Under Review Civil - Reddy
D-07 Flare Stack Foundation Grid F-8 / Flare Missing Design: 4 anchor bolts → Actual: 2 bolts installed 2 Missing 0 NCR Raised Struct. - Iyer
D-08 Weighbridge Approach Slab Gate / Entry Dimension Design: 200mm thick → Actual: 175mm avg 25 mm Thin 15 mm Open Vendor - ABC
Showing 8 of 23 deviations (5 Open, 3 Under Review, 2 NCR, 1 Closed)