Schedule Dashboard
Area variance + S-curve • Planned vs Actual % • Days ahead/behind • Delay alerts
Overall Progress
67 %
▼ 8% behind baseline
Schedule Variance
-24 days
Critical path delayed
Areas On Track
3 / 8
5 areas behind
Active Delay Alerts
7
3 Critical, 4 High
Planned vs Actual by Area
| Area | Planned % | Actual % | Variance | Days Ahead/Behind | Status | Milestone |
|---|---|---|---|---|---|---|
| Digesters (D1-D4) | 95% | 92% | -3% | 12 days behind | At Risk | Mech. Complete: 28 Feb |
| Gas Holder | 80% | 75% | -5% | 18 days behind | At Risk | Inflation: 15 Mar |
| Upgrading / Purification | 70% | 62% | -8% | 28 days behind | Critical | Skid Delivery: 20 Jan |
| Compressor House | 60% | 55% | -5% | 22 days behind | Critical | Install: 10 Feb |
| Cascade Storage | 40% | 38% | -2% | 8 days behind | At Risk | Hydro Test: 25 Mar |
| Dispenser / Filling | 30% | 35% | +5% | 5 days ahead | On Track | Commission: 15 Apr |
| Utilities (Water, Air, Power) | 85% | 88% | +3% | 3 days ahead | On Track | Energization: 31 Jan |
| Roads & Site Development | 50% | 52% | +2% | 2 days ahead | On Track | Final: 30 Apr |
S-Curve: Planned vs Actual Progress
Active Delay Alerts (Early Warnings)
| Alert ID | Area | Priority | Description | Trend | Owner | Since | Action |
|---|---|---|---|---|---|---|---|
| DLY-2026-042 | Upgrading Skid | Critical | Purification skid foundation 9 days behind, trend slipping | 📉 Worsening | Civil - Kumar | 5 days | |
| DLY-2026-045 | Compressor House | Critical | Equipment delivery delayed 3 weeks — vendor force majeure | 📉 Worsening | Procurement - Patel | 3 days | |
| DLY-2026-048 | Gas Holder | Critical | Membrane delivery schedule slipped — customs clearance | → Stable | Vendor - GAIL | 7 days | |
| DLY-2026-041 | Digesters | High | Agitator installation 12 days behind — crane availability | 📉 Worsening | Mech. - Singh | 8 days | |
| DLY-2026-043 | Cascade Storage | High | Hydro-test crew not available until Jan 15 | → Stable | QC - Sharma | 4 days | |
| DLY-2026-046 | Utilities | High | Transformer energization pending SEB approval | 📈 Improving | Elec. - Iyer | 2 days | |
| DLY-2026-047 | Roads | Medium | Asphalt crew mobilized late — monsoon impact | → Stable | Civil - Reddy | 1 day |
Key Milestones (Lender / CFA Linked)
| Milestone | Baseline Date | Forecast Date | Variance | Status | Linked To | Evidence |
|---|---|---|---|---|---|---|
| Digester Mechanical Complete | 28 Feb 2027 | 12 Mar 2027 | 12 days | At Risk | CFA Tranche 2 | |
| Gas Holder Inflation | 15 Mar 2027 | 02 Apr 2027 | 18 days | At Risk | Lender Drawdown | |
| First Gas Production | 15 Apr 2027 | 30 Apr 2027 | 15 days | Critical | CFA Final / SATAT | |
| Commissioning Complete | 30 Apr 2027 | 15 May 2027 | 15 days | Critical | Handover to Ops |