Schedule Dashboard

Area variance + S-curve • Planned vs Actual % • Days ahead/behind • Delay alerts

Overall Progress
67 %
▼ 8% behind baseline
Schedule Variance
-24 days
Critical path delayed
Areas On Track
3 / 8
5 areas behind
Active Delay Alerts
7
3 Critical, 4 High

Planned vs Actual by Area

AreaPlanned %Actual %VarianceDays Ahead/BehindStatusMilestone
Digesters (D1-D4)95%92%-3%12 days behindAt RiskMech. Complete: 28 Feb
Gas Holder80%75%-5%18 days behindAt RiskInflation: 15 Mar
Upgrading / Purification70%62%-8%28 days behindCriticalSkid Delivery: 20 Jan
Compressor House60%55%-5%22 days behindCriticalInstall: 10 Feb
Cascade Storage40%38%-2%8 days behindAt RiskHydro Test: 25 Mar
Dispenser / Filling30%35%+5%5 days aheadOn TrackCommission: 15 Apr
Utilities (Water, Air, Power)85%88%+3%3 days aheadOn TrackEnergization: 31 Jan
Roads & Site Development50%52%+2%2 days aheadOn TrackFinal: 30 Apr

S-Curve: Planned vs Actual Progress

TODAY (18 Nov) Planned Baseline Actual Progress 100% 80% 60% 40% 20% 0% Oct Nov Dec Jan Feb Mar Data Date: 18 Nov 2026 Planned: 78% | Actual: 67%

Active Delay Alerts (Early Warnings)

Alert IDAreaPriorityDescriptionTrendOwnerSinceAction
DLY-2026-042Upgrading SkidCriticalPurification skid foundation 9 days behind, trend slipping📉 WorseningCivil - Kumar5 days
DLY-2026-045Compressor HouseCriticalEquipment delivery delayed 3 weeks — vendor force majeure📉 WorseningProcurement - Patel3 days
DLY-2026-048Gas HolderCriticalMembrane delivery schedule slipped — customs clearance→ StableVendor - GAIL7 days
DLY-2026-041DigestersHighAgitator installation 12 days behind — crane availability📉 WorseningMech. - Singh8 days
DLY-2026-043Cascade StorageHighHydro-test crew not available until Jan 15→ StableQC - Sharma4 days
DLY-2026-046UtilitiesHighTransformer energization pending SEB approval📈 ImprovingElec. - Iyer2 days
DLY-2026-047RoadsMediumAsphalt crew mobilized late — monsoon impact→ StableCivil - Reddy1 day

Key Milestones (Lender / CFA Linked)

MilestoneBaseline DateForecast DateVarianceStatusLinked ToEvidence
Digester Mechanical Complete28 Feb 202712 Mar 202712 daysAt RiskCFA Tranche 2
Gas Holder Inflation15 Mar 202702 Apr 202718 daysAt RiskLender Drawdown
First Gas Production15 Apr 202730 Apr 202715 daysCriticalCFA Final / SATAT
Commissioning Complete30 Apr 202715 May 202715 daysCriticalHandover to Ops